September 2016

September saw most work on pole barn getting done.  Still waiting on electric service install.  Preparations for pouring floor started on the 15th. with arrival of foam board insulation.

Foam insulation for floor.
Foam insulation for floor.

On the 27th. floor drain, Foam insulation, and pex tubing were installed.

Floor Drain and radiant floor heating being installed.
Floor Drain and radiant floor heating being installed.

Floor is ready for wire and concrete.

Came back the 28th. to finish floor.

First of three mixers arrives.
First of three mixers arrives.
Almost half poured.
Almost half poured.
Emptying second truck.
Emptying second truck.
All poured and setting.
All poured and setting.
Finishing up.
Finishing up.

September finally saw rain, in a day and a half we got 3.5 inches.  On the 30th. more stone for driveway was delivered.

Tri-axle dump truck and 3.5 inches of rain.
Tri-axle dump truck and 3.5 inches of rain.

That’s it for September.